As an ISP we use back-haul carriers to connect your premises/phone line to our network. The two carriers we use are TalkTalk Business and BT Wholesale.
To increase our capacity we are working with BT to upgrade our existing connections from multiple 1Gb/s hostlinks to multiple 10Gb/s hostlinks.
This page will follow the progress of this project as the various steps are carried out.
We also have a status page open for this work: https://aastatus.net/32151
☑ Order hostlinks. Completed: 2019-07-12
☑ Connect to A&A equipment. Completed: 2019-10-08.
☑ Configure with BT. Completed: 2019-10-15
☑ Test with BT and finalise test-configuration.
☑ Test with some tame customers.
☑ Finalise configuration
☑ Move all LNSs over to use new hostlinks.
☑ Order hostlinks. Completed: 2019-07-12
☑ Connect to A&A equipment.
☑ Configure with BT.
☑ Test with BT and finalise test-configuration.
☑Test with some tame customers.
☐Finalise configuration
☐ Move all LNSs over to use new hostlinks.